Rebar cages staged along a site road at a data center project

Point Pleasant Data Center

About 7,000 tons for a hyperscale data center: drilled pier foundations and structural foundation pads.

Bid a job like this
The job

7,000+ tons, placed to schedule.

Point Pleasant, WVSee it on the project map

Suncoast installed approximately 7,000 tons of reinforcing steel for a hyperscale data center. Scope included drilled pier foundations for Kiewit and structural foundation pads for Ames Construction.

  • SectorData Centers/Technology
  • CustomerAmes Construction, Kiewit
  • ScopeRebar Placement & Installation, Deep Foundations & Drilled Piers, Mass Concrete & Mat Foundations
  • Work includedDrilled piers, Foundation pads
On site